Project Management, Construction Process and Responsibilities in Mallorca

project management and construction process in Mallorca

Responsibilities and structure

A building project is never just design and execution. It is always also a process of decisions, coordination, deadlines, budgets and responsibilities. That is exactly why project management in Mallorca is so often underestimated – although in practice it decides between calm and friction.

The higher the standard, the more important the management. Many Mallorca projects are run from abroad. Without clear responsibilities, a project loses calm, direction and quality. (Web GOIB). That is why jle combines architecture with on-site project management.

Who has which role in the project

The architect develops the design. The lawyer checks ownership, contracts and legal position. The tax adviser classifies structure and tax consequences. A project manager or client representative keeps deadlines, costs, interfaces and decision paths together.

Why clear responsibilities matter so much

Many problems do not arise because nobody is responsible, but because several parties understand different things by responsibility. The earlier roles and communication paths are defined cleanly, the lower the risk of idle time and misunderstandings.

Project management matters above all for clients

International owners in particular benefit when someone structures the project in the client’s interest and does not merely handle individual specialist services. This is especially valuable when owners are not permanently on site. jle therefore offers architecture and project management as one integrated service.

The LOE expressly organises the roles in the Spanish building process. Among others, it distinguishes between promotor, project author, site management (director de obra) and technical execution management (director de ejecución de obra). This separation is not a formality. It is the basis for decisions, liability and execution fitting together. (Web GOIB)

Since 2024 the Balearic government has additionally relied on organisational acceleration. That is precisely why the internal project structure is even more important today. Anyone who wants to use administrative simplification must organise approvals, documents and interfaces all the more cleanly. (Web GOIB)


1. Basic principle: project management is not a substitute for the statutory roles


2. Statutory division of tasks among the main parties

Client / promotor

Rule of thumb:

The client can delegate tasks but cannot lose overall responsibility as promotor.

Architect / arquitecto / proyectista / director de obra

Technical architect / arquitecto técnico / aparejador / director de ejecución

Rule of thumb:

The architect is responsible for the overarching project and design logic; the technical architect controls the concrete execution, quantities, quality and building reality.

Contractor / constructor / contratista

Rule of thumb:

The contractor is the party that executes, not a neutral inspector of their own work.

Health and safety coordinator / coordinador de seguridad y salud


3. Project management – useful, but delimit it cleanly in the contract

Project management is often very sensible for private building projects in Mallorca, but it has no authority of its own and does not replace, in law, the tasks of the architect, the technical architect, the lawyer or the tax adviser. If one compares the scopes of services of architects and technical architects in Spain with those customary in Germany under the HOAI, the areas of competence and responsibility are not identical but in part different. Additional project management in Spain can therefore help to balance these differences, coordinate interfaces and bundle the client’s interests effectively, which is why jle offers project management as part of additional architect services.

Typical tasks:

Not its task:


4. Why the contractor is not the best choice for project management

A contractor can organise the construction. But they should not steer it alone. Serious project management separates execution, technical control, contract control and economic client representation.


5. Separation of powers in the building project

Technical power

Contractual power

Economic power

Authority power


6. Interplay of architect, project management, lawyer and tax adviser

Architect

Project management

Lawyer

Tax adviser


7. Construction process – typical management phases

Phase 1: Plot and feasibility

Phase 2: Project definition

Phase 3: Permit project

Phase 4: Execution project

Under Balearic law the execution project must fully develop the básico; it must not worsen or change the approved uses and conditions. Once submitted to the Ayuntamiento, the technical project becomes the official document, for whose technical correctness the author is responsible. (Web GOIB)

Phase 5: Tender and award

Phase 6: Start of construction

Phase 7: Construction execution

Phase 8: Acceptance and final documentation


8. Rights and duties on site

Client / promotor

Architect / director de obra

Technical architect / director de ejecución

Safety coordinator

Contractor

Subcontractors

The Spanish subcontracting regulation requires, among other things, own organisation, resources, preventive training and registration in the register of accredited companies; subcontracting chains and the Libro de Subcontratación are also regulated by law. (BOE)


9. Internal reference:


10. Core statement

When building in Mallorca, security does not arise from one strong individual but from clean separation of tasks. The architect leads the project technically and in design terms, the technical architect controls execution and quality, the contractor builds, the project manager steers costs, deadlines and communication, the lawyer secures contracts and building law, the tax adviser checks IVA, ITP, AJD and payment structure. Only this separation makes a building project controllable.

FAQ

Is a good architect enough without project management?

For small projects this can be sufficient. For more complex projects, additional management is often a great advantage. jle then offers project management as well.

Is project management only sensible for luxury projects?

No. It is helpful wherever several parties have to be coordinated.

A good project does not run by itself – it is well led.

talk to us

Request the guide to building in Mallorca and the Balearics

or

create a jle online checklist

building in Mallorca and the Balearics checklist

back to the building in Mallorca guide

References

Ley de Ordenación de la Edificación BOE Roles and responsibilities

Ley 7/2024 CAIB New Balearic organisational framework

ECU information CAIB Procedure acceleration and ECU